Quaise Energy has signed Google as the first customer for Project Obsidian, a geothermal power project near Newberry in central Oregon, with the company agreeing to buy 50 MW of the plant’s output. Those 50 MW are nameplate capacity from a project that is not yet built, using a drilling method the Houston firm has not yet run to full depth at commercial scale – and it matters now because data-centre load in Oregon is climbing against a 2040 clean-electricity mandate that leaves few firm, weather-independent resources to meet it.
Melting rock instead of cutting it
A geothermal well is a hole in hot rock, and the hole is the expensive part. Conventional drilling turns a steel bit against stone; the bit wears, and at the temperatures Quaise is chasing – above roughly 400°C – the seals in a drill string and the electronics in logging tools fail before the rock does. Quaise’s substitution is to stop cutting and start melting. A gyrotron, a vacuum-tube device that emits a beam of millimetre-wave energy in the same part of the spectrum a microwave oven uses but at hundreds of kilowatts to about a megawatt rather than one, is lowered into the hole and aimed at the rock face. The rock absorbs the beam and fractures and vaporises; melt running down the wall solidifies into a glassy liner that cases the borehole as the well deepens. Drilling becomes a thermal process, so the depth limit stops being bit life and becomes the power supply and the beam delivery.
Compare what the industry does today. Most geothermal plants run on hydrothermal reservoirs – rock that is hot, naturally permeable and already holding water. All three together are rare, which is why the U.S. fleet clusters in Nevada, California, Utah and a handful of other states. Enhanced geothermal systems (EGS) relax the second condition by fracturing hot rock, much as the shale industry fractures tight formations; Fervo Energy’s wells in Nevada are the best-known current example. Both approaches generally stop at roughly 2-4 km, where temperatures sit in the 150-250°C range. Go deeper and the physics changes: past about 374°C and 22 megapascals, water becomes supercritical – neither liquid nor gas – and a kilogram of it carries several times the heat energy available to a turbine compared with the 200°C brine a conventional flash plant uses. That ratio, not the depth itself, is the commercial argument: fewer wells for the same megawatts. Newberry, a volcanic caldera with recent eruptive history and correspondingly high heat flow, is one of the few places in the Pacific Northwest where the shallow geology already hints at that prize.
How far the gyrotron has actually been pushed
Separating what has been demonstrated from what has been announced is the whole exercise here.
- Maturity: Public evidence of the method sits at bench and laboratory scale – rock melted by a gyrotron beam in a test cell, not kilometres of hole in a caldera. Project Obsidian is described as Quaise’s first commercial project, so the step being attempted is from surface trial to a full-depth well tied to a turbine, and 50 MW of nameplate capacity implies more than one well rather than one good hole.
- Cost position: No $/MWh price accompanied the Google agreement, and no unsubsidised levelized cost of energy (LCOE) has been published for Project Obsidian, so its economics remain undisclosed. For scale, U.S. geothermal power purchase agreements have generally settled in the roughly $60-$100/MWh band in recent years, while the Department of Energy’s Enhanced Geothermal Shot aims at about $45/MWh by 2035; any eventual LCOE figure will also need a subsidy note, since geothermal qualifies for the federal clean electricity investment tax credit (ITC) or production tax credit under the Inflation Reduction Act, and I would assume Obsidian claims one of them.
- Scaling constraint: The bottleneck is hardware, not hot rock. Megawatt-class gyrotrons are built in small numbers for fusion research and industrial heating, downhole seals and electronics must survive above 400°C, and the rigs and crews still come from oil and gas. None of those supply chains scales on a data-centre timetable.
What a Newberry plant displaces in Oregon, and what it needs first
If the wells work, the first thing displaced is not baseload coal but the firming capacity Oregon would otherwise build: gas-fired combustion turbines and the multi-hour batteries that make solar deliverable after the sun drops behind the Cascades. Data-centre growth in the Columbia and Deschutes basins has pushed both PacifiCorp and Portland General Electric into procurement cycles dominated by solar-plus-storage and gas, and firm, weather-independent output at a high capacity factor is the one product neither fully supplies. The second displacement is subtler and is my inference rather than a reported fact: Google’s 24/7 carbon-free energy goal, which requires hourly matching on each grid where it operates, is easier to hit with a resource that runs through the night than with an equivalent volume of solar plus renewable energy credits.
The dependencies are ordinary and unforgiving. A 50 MW plant needs an interconnection agreement and transmission capacity to move power from the Newberry area north toward the load, whether that is PacifiCorp’s system, Portland General Electric’s, or the Bonneville Power Administration’s federal marketing of hydro. Land status around Newberry – a patchwork of national forest, the Newberry National Volcanic Monument administered by the U.S. Forest Service, and private timberland – sets the permitting clock. And a power purchase agreement sized in megawatts of capacity is not the same as a plant sized in gigawatt-hours of annual delivery; hyperscale campuses draw hundreds of megawatts, so 50 MW reads as a first tranche, not a supply solution.
Four things that would turn the Google deal into a power plant
- A full-depth well with published temperature and flow logs, verified by a third party rather than by the company that drilled it.
- An independent reservoir report of the kind lenders commission – an engineer’s certificate tying measured flow and enthalpy to the 50 MW headline.
- A definitive power purchase agreement with a price, an in-service date and an interconnection agreement, because an offtake announcement is not a signed contract with delivery risk allocated.
- Cost per metre drilled repeated across several wells. One successful hole proves the physics; it does not prove the business.
Who should watch this one
- Data-centre energy procurement teams: 50 MW of round-the-clock capacity reduces the storage and credit volume needed for hourly clean-energy matching, so the relevant question is not the headline megawatts but the guaranteed capacity factor and the curtailment terms in the contract.
- Resource planners at PacifiCorp, Portland General Electric and BPA: a firm, small-footprint resource would change winter adequacy maths in the Western Interconnection and the 2030 and 2035 milestones in Oregon’s clean-electricity law – but only after a well test, not before.
- Drilling contractors and oilfield service firms: if melt-drilling works, value migrates from bits and rig crews toward gyrotron manufacturing and high-temperature completions, which is a different supplier base than the one serving hydrothermal drilling today.
Bottom line
Google’s commitment is an option on a drilling method, packaged as a power contract, and the price of that option is not disclosed. Project Obsidian’s 50 MW would be a modest plant by any measure, yet it would be the first commercial test of whether rock can be melted at depth and turned into a well that holds pressure. Superhot geothermal remains a laboratory result with a site and a customer attached; the distance to mattering is measured in one deep hole, one independent flow test, and one repeatable cost per metre.
Read the full report at Energy News Network
Note: facts and figures attributed above to Energy News Network reflect that outlet's original reporting. Other figures and quotes are attributed inline to the pages they came from and listed under Sources consulted. Broader context, cross-sector connections, and forward-looking scenarios are analysis and interpretation, not original reporting.